Milestone 2 Exit Criteria

Features: (not comprehensive)

  • First integration of Tango (not feature complete)
  • MQ integration (not feature complete)

Reviews:

  • One Pagers reviewed by community
  • reviewed and approved by AS Architects
  • Start user experience reviews

Bugs:

  • No P1's.
  • 50% reduction in P2s from the baseline. Any open P2's should be in a state 3 (evaluated) or higher. (The baseline is start of Milestone 2)
  • 10% reduction in P3s per module from the baseline (by way of fixing, downgrading or closing).
  • 40% of all P3's must be evaluated by the end of M2
  • Forward port ALL P2 bugs from 8.2 branch

CTS:

  • Run 1 combination of all tests - pass or don't pass. Will take 4 days.

Big Apps:

  • Try a run for all Big Apps

Performance

  • Need baseline numbers. No regression from AS9.0.

Documentation:

  • Drafts of docs for features by 9/25/06.
    • in pre-beta quality
    • if engineering has not provided input, the feature may be thinly documented
    • docs will only be reviewed for accuracy