Relevant Specification Dates
Item |
Date |
Specification PFD Date |
March 15, 2009 |
Mojarra Milestone Dates
Milestone |
Date |
Status |
Feature complete with respect to 2.0 PR requirements |
Dec 15, 2008 |
COMPLETE |
*RELEASE* Mojarra 2.0.0 PR release on Java.net and UC2 |
Dec 19, 2008 |
COMPLETE |
Feature complete with respect to 2.0 PFD requirements |
TBD |
*RELEASE* Mojarra 2.0.0 Beta release on Java.net and UC2 |
TBD |
Final Ballot for 2.0 Specification |
May 8, 2009 (ballot period of 14 days) |
RI/TCK Hand-off to JCP |
May 22, 2009 |
*RELEASE* Mojarra 2.0.0 final release |
TBD |
Major Tasks
Task |
Start Date |
End Date |
Status |
Merge AJAX Branch into Trunk |
Dec 8, 2008 |
Dec 9, 2008 |
COMPLETE |
Bug Swat (both Mojarra/Facelets) |
Feb 2, 2009 |
Mar 2, 2009 |
IN PROGRESS |
Merge State Saving Branch into Trunk |
Feb 5, 2009 |
Feb 6, 2009 |
COMPLETE |
Acceptance/End-to-End Testing |
TBD |
TBD |
Not Started |
Create a Facelets Doc Tool similar to TLDDoc (Ryan,Jim) |
NOW |
Feb 20 |
Not Started |
Migrate TLD documentation to new format (Ed,Roger) |
FEB 23 |
Feb 27 |
IN PROGRESS |
Conditional Navigation from JBOSS |
NOW |
Feb 6 |
COMPLETE |
Bookmarability from JBOSS |
NOW |
Feb 12 |
JBOSS - COMPLETE |
View Parameters from JBOSS |
NOW |
Feb 12 |
JBOSS - COMPLETE |
Bean Validation Integration from JBOSS |
NOW |
Feb 12 |
JBOSS - COMPLETE |
Portlet Integration (Spec/Impl Changes) from LifeRay |
NOW |
Feb 12 |
LIFERAY - COMPLETE (Single Portlet Ajax) |
VAST - Ken Paulsen |
NOW |
Feb 14 |
DEFERRED TO 2.1 |
Client Component Behavior |
NOW |
Feb 14 |
COMPLETE |
Open Issues (bugs, features, etc) for 2.0
Notes
- We will be integrating into v3 at intervals more frequent than the major release milestones listed above. We (the RI team) will communicate any changes or new features that are part of these integrations to the SQE and TCK teams so their work can adjust as necessary.
- All promoted builds are being pushed to UC2 so developers testing 2.0 will have access to the latest promoted bits
- After SCF change bundles for any change will be required
- After HCF all changes must be approved by Ryan before being checked in
|