openInstaller 1.0 High Level Schedule
Item |
Date |
Description |
0.9.1 release |
June 4, 2007 |
Announcement |
0.9.2 gate freeze |
June 21, 2007 |
Only critical bug fixes for MQ customer |
0.9.2 release |
July 12, 2007 |
Release with complete Upgrade and JDK selection support. All MQ P1-P3 bugs delivered. |
1.0 Gate Freeze |
July 31, 2007 |
All Portal features delivered. JNLP support Delivered |
1.0 Testing Complete |
August 10, 2007 |
Full Unit, Regression, Feature testing completed |
1.0 Release |
August 13, 2007 |
Features include product selection, JNLP support, Patch install |
openInstaller 1.0 Detailed Feature Schedule
Complete? |
Item |
Date |
Owner |
Team |
Description |
Yes |
Upgrade |
May 31, 2007 |
Radhika |
Sandeep |
Upgrade support for legacy and existing OI installed products. Delivered in 0.9.2 |
Yes |
JDK Selection |
May 31, 2007 |
Gustave |
|
Detect and allow for selection of existing JDK's. Delivered in 0.9.2 |
Yes |
L10N Selection |
July 3, 2007 |
Gustave |
|
Provide ability to installer or not the L10N deliverables. |
Yes |
MQ P1-P3 bug fixing |
July 3, 2007 |
Matt |
All |
Meet ship requirements for MQ release |
Yes |
Response file support |
July 3, 2007 |
James |
|
Allow specification of a response file generated from config steps. RFE 6571850 |
Yes |
Namespace update |
July 3, 2007 |
Jayanth |
|
Change com.sun to org.openinstaller |
NO |
P3 bug fixes cutoff |
July 20, 2007 |
All |
|
All P3's fixed. |
Yes |
Product Selection |
July 27, 2007 |
Manpreet |
Rajkumar |
Allow user to select products to install. Including ability to do multi session installations. Also move L10N Selection checkbox to this page. See RFE 6515385. |
NO |
Bootstrap Install via http |
July 27, 2007 |
Jayanth |
|
Ability to pull down the engine using JNLP script and have the engine retrieve from the server all the rest of the needed parts, including packages. |
NO |
Dynamic Progress Support for Configuration |
July 27, 2007 |
Sandeep |
James |
Provide interface for configurators to accurately update progress |
NO |
P1-P2 and S1 bug fixes cutoff |
July 27, 2007 |
All |
|
All P1-P3's fixed. |
Yes |
Zip Install, All Platforms |
Kaarthikraaj |
July 27, 2007 |
|
Allow for zip packages for all platforms |
Yes |
LSARC commitment for Engine and SIMS |
July 27, 2007 |
James |
Inception schedule for July 31, 2007 (July 24 LSARC agenda was full) |
|
Yes |
LSARC fast tracks for JDK Selection, Upgrade, L10N Selection |
July 27, 2007 |
Radhika, Gustave |
|
new features |
NO |
LSARC fast tracks for PSP, Bootstrap Install, Zip Install |
August 10, 2007 |
Manpreet, Jayanth |
|
Items deferred to post-1.0
Complete? |
Item |
Date |
Owner |
Team |
Description |
No |
Patch installation |
July 27, 2007 |
Gustave |
|
Installables should be able to include patches as issued by Sun. RFE 6514787. |
|