Prototype Phase: Mar-Apr 2010

1. Write up user scenario document and send for review (by April 2nd).

2. Incorporate comments and finalize the user scenario document (by April 15th)

3. Implement of some of the basic scenarios (deploy/undeploy?) and send code for review (by April 20th)

4. Incorporate review comments and check in code (by April 30th)

Functional Specs: Apr-May 2010

1. Write up Functional Spec (revise original one pager and then add user scenario document) and send for review (by May 14th)

2. Internal Review and incorporate comments (by May 21th)

3. Go to asarch for review, incorporate comments and finalize the functional spec (by May 30th)

Development Phase: May-Dec 2010

Soft Code Freeze: September 2010

1. Basic functionality: (by June 21th)

2. Clustering functionality (by August 16th)

Hard Code Freeze: November 2010

1. Fix P1-P3 issues

Release: December 2010