*Milestone* *Target Date* *Status* *Feature list*
1 MS1 Aug 14, 2006 Released (Aug 16, 2006) LB Admin, HADB Admin (internal), GF with Clustering, Enable new WS stack
2 MS2 freeze Sept 12, 2006 Done (Sept 12) WSIT integration, Remove NSS
2 MS2 complete Sept 26, 2006 Released (Sept 27) Milestone 2 Exit Criteria
3 MS3 freeze (feature Complete) Nov 21, 2006 Done ALL Features complete. GFv2 Feature Complete Exceptions
3 MS3 Complete Dec 11, 2006 Done Milestone 3 Exit Criteria
4 MS4 Jan 22, 2007 Done Milestone 4 Exit Criteria
5 Beta1 Mar 12, 2007 Done Feature Testing complete. No P1, P2
6 Beta2 May 3, 2007 Done Feature Testing complete. No P1, P2.
7 Beta3 Jul 9, 2007 Done Fully featured enterprise beta. No P1, P2.
8 RC1 Aug 5, 2007 Done Release Candidate 1
9 RC2 Aug 9, 2007 Done Release Candidate 2
10 RC3 Aug 15, 2007 Done Release Candidate 3
11 RC4 Aug 22, 2007 Done Release Candidate 4
12 RC5+ -- on going Release Candidate 5 and additional RCs may be needed
13 FCS Sept 17, 2007 -- No P1, P2, P3. Solid Product. FCS.

---------------